Construction Dashboard Project Details |
| UPC |
56231 |
Contract Id: |
D00056231C04B |
State Project # |
6460-013-F16,C504,B619,B627 |
| Related UPCs |
|
|
| Summary |
| Description |
RTE 460 RELOC: INC. GR., DR., ASP. PAVE (Lebanon, Buchanan County) (6460-013-F16,C504,B619,B627) |
| District |
Bristol |
Residency |
LEBANON |
| County |
BUCHANAN |
City/Town |
|
| Road System |
Primary |
Route |
6460 |
| Contract Type |
CONSTRUCTION RAAP (CR) |
Type of Work |
GRADE / DRAIN / PAVE |
| Comments |
|
|
| Contact Information |
| VDOT Contact |
Conrad Hill |
Phone |
(276) 889-7601 |
| Contract Manager |
|
| Contact Information |
|
| Construction Company |
BIZZACK, INC. |
| Construction Company |
|
| Locality / Project Web Site |
|
| VDOT Contact |
Conrad Hill |
Phone |
(276) 889-7601 |
|
| Budget |
| Award |
$24,246,554 |
| Cost of Work To Date |
|
| Un-audited Final Cost |
$23,418,263
|
| Current Contract Amount |
$24,529,427 |
| Source of Projection |
Data Warehouse |
|
< 10% OVER ORIGINAL CONTRACT AWARD AMOUNT
|
|
|
|
| Schedule |
| Contract Execution Date
* |
March 24, 2006 |
| Original Specified Completion Date |
July 15, 2009 |
| Current Estimated Completion Date |
|
| Current Specified Completion Date |
July 15, 2009 |
| Acceptance Date |
July 15, 2009 |
| % Work Completed |
|
| % Original Time Spent |
|
| Days Charged To Date |
1210 days |
| Original # Days Allowed |
1210 days |
| Type of Schedule Days |
Fixed Date |
| Schedule Source |
Straight Line |
| *Actual work on this project may begin at any time after contract execution |
|
ACCEPTANCE DATE <= ORIGINAL COMPLETION DATE
|
|
|
|
|
|
|